Friday, 20 April 2012

Project cam time lapse videos and extra pics ...

Nick got the time lapse pictures working and has posted on you tube:

Movie 01 - Slab.
Aug 30 - Sept 11, 3 hr intervals. 0:27 mins.
Piles already in: clay board laid, steel work assembled, shuttering assembled, slab poured.

Movie 02 - Rammed earth wall mark 1.
Sep 14 - Sep 27. 3 hr then 1 hr intervals. 1:48 mins.
Glass foam base fitted, shuttering assembled, ramming, scaffolding assembled, more shuttering, more ramming, shuttering comes off, wall falls down, earth cleared.

Movie 03 - Rammed earth wall mark 2, SIPs construction.
Oct 14 - Nov 5, 1 hr then 30 min intervals. 3:04 mins.
REW2 shuttering & scaffolding in place, ramming of 1st 2.7 metres, scaffolding for SIPs assembled, REW2 pt 1 shuttering removed, ground floor SIPs and 1st storey floor and gable ends assembled, REW2 pt 2 shuttering and ramming.

Movie 04 - Cladding.
Jan 9 - Feb 9, 30 min intervals. 2:41 mins.
Breather membranes, battening, slate roof and western red cedar boards.

These are just some extra pics as it's been a couple of weeks since the last post.






No comments:

Post a Comment